大学职业资格刷题搜题APP
下载APP
课程
玩着学单词
题库模板
WORD模板下载
EXCEL模板下载
视频教程
创建题库
登录
logo - 刷刷题
创建自己的小题库
搜索
【单选题】

A project manager completes a project. Organizational policies require documentation of performance reviews and lessons learned for every completed project.These are tools and techniques for which of the following processes?

A.
Contact closes
B.
Administrative closure
C.
Performance audit
D.
Formal acceptance
手机使用
分享
复制链接
新浪微博
分享QQ
微信扫一扫
微信内点击右上角“…”即可分享
反馈
收藏 - 刷刷题收藏
举报
刷刷题
参考答案:
举一反三

【单选题】Which of the following is correct for the WBS?

A.
Work component descriptions are often collected in a WBS dictionary.
B.
WBS is the input of defining scope.
C.
The lowest level of WBS is work packages and cannot be further decomposed.
D.
The work not being included in WBS may not be outside the scope of the project.

【单选题】How should a project manager interpret an 8-point run in a process with 1 point located out of control limit?

A.
It is a normal situation, nothing should be done.
B.
Control limits should be widened.
C.
It is an abnormal situation; production processes should be corrected.
D.
It is a warning signal; quality measurement systems should be updated.

【单选题】Which evaluation technique is used as an essential planning component of controlling Schedule ?

A.
Schedule management plan
B.
Estimate at Completion (EAC)
C.
Actual Cost of Work Performed (ACWP)
D.
Variance analysis

【单选题】Of the options below, what is the most significant action the project manager will take for a virtual team project?

A.
Send a project plan to all members.
B.
Develop a communication management plan.
C.
Obtain and analyze team members’ expectations.
D.
Review the team members’ skill.

【单选题】All of the following are common results of risk management EXCEPT?

A.
Contract terms and conditions are created.
B.
The project management plan is changed.
C.
The communications management plan is changed.
D.
The project charter is changed.
相关题目:
【单选题】Which of the following is correct for the WBS?
A.
Work component descriptions are often collected in a WBS dictionary.
B.
WBS is the input of defining scope.
C.
The lowest level of WBS is work packages and cannot be further decomposed.
D.
The work not being included in WBS may not be outside the scope of the project.
【单选题】How should a project manager interpret an 8-point run in a process with 1 point located out of control limit?
A.
It is a normal situation, nothing should be done.
B.
Control limits should be widened.
C.
It is an abnormal situation; production processes should be corrected.
D.
It is a warning signal; quality measurement systems should be updated.
【单选题】Which evaluation technique is used as an essential planning component of controlling Schedule ?
A.
Schedule management plan
B.
Estimate at Completion (EAC)
C.
Actual Cost of Work Performed (ACWP)
D.
Variance analysis
【单选题】Of the options below, what is the most significant action the project manager will take for a virtual team project?
A.
Send a project plan to all members.
B.
Develop a communication management plan.
C.
Obtain and analyze team members’ expectations.
D.
Review the team members’ skill.
【单选题】All of the following are common results of risk management EXCEPT?
A.
Contract terms and conditions are created.
B.
The project management plan is changed.
C.
The communications management plan is changed.
D.
The project charter is changed.
刷刷题-刷题-导入试题 - 刷刷题
参考解析:
题目纠错 0
发布
刷刷题-刷题-导入试题 - 刷刷题刷刷题-刷题-导入试题 - 刷刷题刷刷题-刷题-导入试题 - 刷刷题
刷刷题-刷题-导入试题 - 刷刷题
刷刷题-刷题-导入试题 - 刷刷题
刷刷题-单词鸭