大学职业资格刷题搜题APP
下载APP
课程
玩着学单词
题库模板
WORD模板下载
EXCEL模板下载
视频教程
创建题库
登录
logo - 刷刷题
创建自己的小题库
搜索
【单选题】

When is an appropriate time to hold the kick-off meeting?

A.
After the preliminary planning ,but before execution
B.
When the project manager has positive news to share
C.
Before the project chart is signed
D.
After the communications plan has been developed
手机使用
分享
复制链接
新浪微博
分享QQ
微信扫一扫
微信内点击右上角“…”即可分享
反馈
收藏 - 刷刷题收藏
举报
刷刷题
参考答案:
举一反三

【单选题】During project execution, the customer wants to make a change in the project scope. What should the project manager do?

A.
Ask for a change request
B.
Advise the customer that there is no possibility for changes while the project is underway.
C.
Rewrite the project plan with the new requirements and implement it.
D.
Involve top management to plan a new budget and resources.

【单选题】A high performing project is almost in the completion stage when the sponsor requests a minor change. What should the project manager do first?

A.
Deny the request
B.
Refer to the management to decide
C.
Allow the team to handle
D.
Explore, clarify, and define the problem

【单选题】Project change control is part of which of the following plans?

A.
Quality management
B.
Risk management
C.
Configuration management
D.
Communication management

【单选题】As of the fourth month on the Acme project, cumulative planned expenditures were ¥100,000. Actual expenditures totaled ¥120,000. How is the Acme project doing?

A.
It is ahead of schedule.
B.
It is in trouble because of a cost overrun.
C.
It will finish within the original budget.
D.
The information is insufficient to make an assessment.
相关题目:
【单选题】During project execution, the customer wants to make a change in the project scope. What should the project manager do?
A.
Ask for a change request
B.
Advise the customer that there is no possibility for changes while the project is underway.
C.
Rewrite the project plan with the new requirements and implement it.
D.
Involve top management to plan a new budget and resources.
【单选题】A high performing project is almost in the completion stage when the sponsor requests a minor change. What should the project manager do first?
A.
Deny the request
B.
Refer to the management to decide
C.
Allow the team to handle
D.
Explore, clarify, and define the problem
【单选题】Project change control is part of which of the following plans?
A.
Quality management
B.
Risk management
C.
Configuration management
D.
Communication management
【单选题】As of the fourth month on the Acme project, cumulative planned expenditures were ¥100,000. Actual expenditures totaled ¥120,000. How is the Acme project doing?
A.
It is ahead of schedule.
B.
It is in trouble because of a cost overrun.
C.
It will finish within the original budget.
D.
The information is insufficient to make an assessment.
刷刷题-刷题-导入试题 - 刷刷题
参考解析:
题目纠错 0
发布
刷刷题-刷题-导入试题 - 刷刷题刷刷题-刷题-导入试题 - 刷刷题刷刷题-刷题-导入试题 - 刷刷题
刷刷题-刷题-导入试题 - 刷刷题
刷刷题-刷题-导入试题 - 刷刷题
刷刷题-单词鸭