As of the fourth month on the Acme project, cumulative planned expenditures were ¥100,000. Actual expenditures totaled ¥120,000. How is the Acme project doing?
A.
It is ahead of schedule.
B.
It is in trouble because of a cost overrun.
C.
It will finish within the original budget.
D.
The information is insufficient to make an assessment.