A project is completed, however, the project was delayed, causing cost overruns at the end of the project.What should the project manager do in this case?
A.
Document the circumstances as lessons learned
B.
Focus attrition on archiving the financial records for this project
C.
Evaluate at the work of the project and compare the results to the project scope
D.
Document the circumstances surrounding project completion during the validate scope process.